2019-2020 Home Bank Remodel

Phase 1
Phase 2
Phase 3
(01/2020)
Aug 14-22: 3rd Floor Demo - COMPLETEOctober: All Exterior Demo - COMPLETE
Aug 22-28: 3rd Floor Framing - COMPLETEOctober: Roof - IN PROGRESS
Aug 14-Sept 6: 3rd Floor Plumbing, Electrical, Heating/Cooling - COMPLETEOctober: 1st Floor South Demo - COMPLETE
Sept 18- Oct 1: 3rd Floor Painting, Trim and Flooring - IN PROGRESSOctober: 1st Floor South Framing - IN PROGRESS
Oct 1-Oct 7: 3rd Floor CeilingOctober-November: 1st Floor Plumbing, Electrical, Heating/Cooling


Big Progress in September!

September 30, 2019

 

Exterior Demolition Complete!

 

1st Floor Renovation Underway!

 


3rd Floor Remodel Underway

August 23, 2019

 

Work Area

Before & During

 

Elevator Hall

Before & During

 

Conference Room

Before & During


Temporary Alert!

August 16, 2019

Customers using the Main Office parking lot off of Mulberry Street must exit via Mulberry Street.  Access to the Post Office Box and Washington Street are temporarily blocked.  Thank you for your patience during our remodel!

 


Making Lives Better

August 6, 2019

As reported in the Reporter-Times, an extensive remodel of our main branch in downtown Martinsville is beginning!

Here’s what you need to know:

  1. Our regular business hours will not change.
  2. Entrances may be temporarily obstructed – stay tuned for updates.
  3. Our new facility will empower us to better serve you and our Martinsville community.

 